January 6, 2026

Tanzania’s Gold Refinery Hampered by Raw Material Supply Crisis

0:00

Tanzania’s ambition to become a regional gold refining hub is facing serious setbacks as chronic raw material shortages leave its flagship facility operating far below capacity, despite possessing world-class infrastructure.


The Mwanza Precious Metals Refinery, designed to process up to 480 kilograms of gold daily, is currently operating at just 10–20 per cent capacity, handling between 50 and 100 kilograms per day. In 2025, total throughput stood at 7.429 tonnes, against a theoretical annual capacity exceeding 175 tonnes.
The shortfall is not technical. The refinery consistently achieves international purity standards of 99.999 per cent. Instead, the constraint lies in access to raw gold. Only 2.995 tonnes of purchased gold, valued at $305.9 million, were processed in 2025, underscoring deeper structural weaknesses in Tanzania’s gold supply chain.
Regulatory friction and fiscal disincentives are key drivers.

Current spot price of gold is approximately over $4,000 per ounce. Credit: VladKK/Shutterstock.com

Import levies and administrative complexity continue to divert gold flows toward alternative regional or international refining hubs. A 1 per cent inspection fee alone adds about $63,000 to a typical 100-kilogram gold import, weakening Tanzania’s competitiveness as a refining destination.


The gap between domestic gold production and refinery intake suggests that substantial volumes of locally mined gold bypass domestic processing altogether. This trend reflects inefficiencies in trade facilitation rather than a lack of gold supply.
Ownership structure has also failed to resolve the problem. The refinery’s hybrid model which is 25 per cent state-owned through Stamico and 75 per cent privately held, was intended to balance public policy goals with commercial efficiency. Yet performance indicators show that supply-side bottlenecks persist.
Underutilisation carries heavy economic costs. In 2025, refining services generated Sh2.976 billion, barely 15 per cent of potential earnings at full capacity. Government collections stood at Sh32.4 billion, far below projections of over Sh150 billion under optimal utilisation. Lost capacity also constrains job creation, mining cluster development, and access to favourable processing options for small-scale miners.
While proposed reforms including royalty reductions and removal of inspection fees could redirect gold to domestic refineries, implementation remains pending. Until fiscal, administrative, and liquidity constraints are addressed, Tanzania risks owning modern refining infrastructure that continues to operate as a fraction of its potential.