Sandfire Resources has posted a strong opening to the 2026 financial year, with group copper-equivalent production for the September quarter coming in nearly 5% ahead of plan at 35 500 t, underpinned by solid performance at both its Matsa operation in Spain and the Motheo mine in Botswana.
The company reaffirmed its full-year production, cost and capital expenditure guidance, noting that output remains weighted towards the second half.
“At our full year financial results in August, we noted that copper equivalent production for FY26 would be weighted towards the second half, with a circa 48:52 skew anticipated. We also stressed that the copper equivalent production skew in the first half would be even more acute, with a 45:55 split anticipated across the September and December quarters. Pleasingly, at the end of September, copper equivalent production for the group is tracking almost 5% ahead of plan and remains on track to achieve the mid-point of annual guidance of 157 000 t,” said Sandfire CEO and MD Brendan Harris.

He added that the Motheo operation is gathering momentum. “Our team at Motheo has made strong progress dewatering the A4 pit, with mining having recommenced in Stage 1 in recent days and the proportion of higher grade ore feed expected to rise across the remainder of the year.”
Matsa delivered 21 800 t copper-equivalent — around 23% of its FY26 guidance — in line with mine plans that called for processing more metallurgically complex and lower-grade ore this quarter. Motheo produced 13 600 t, representing 22% of annual guidance, as the processing rate increased to an annualised 5.8-million tonnes. Output is forecast to strengthen in coming quarters as access to higher-grade A4 ore expands.
Sandfire also reported continued cost discipline, with underlying operating unit costs of $85/t at Matsa and $42/t at Motheo — both marginally below full-year forecasts. Motheo’s costs are expected to lift modestly to about $44/t as haulage distances and handling requirements increase with the A4 ramp-up.
“Importantly, our team’s unrelenting focus on the basics continues to feed through to our balance sheet, where net debt declined by a further $61-million to finish the period at $62-million, for a cumulative $283-million reduction in net debt across the past year,” Harris said.
For the quarter, Sandfire recorded unaudited group sales revenue of $328-million and underlying operations Ebitda of $157-million, resulting in underlying group Ebitda of $137-million.
Botswana’s updated Mines and Minerals (Amendment) Act — in force from October 1— introduces new licence conditions including a higher government option of up to a 24% working interest, increased stakes for citizen-owned companies and a 10 000 km² ceiling on prospecting licence holdings. Sandfire confirmed that these changes will not affect its current operations, as licences for the T3 and A4 openpits are already in place. The company holds 13 052 km² under prospecting licences and is relinquishing lower-priority areas in line with its exploration strategy.