Stakeholders have continued to express divergent views over the 2026 budgetary allocation to the non-functional Ajaokuta Steel Company Limited (ASCL).

Established in 1979, ASCL remains a strategic national asset conceived to drive Nigeria’s industrial modernisation.
The company received N6.69 billion in the 2026 Appropriation Bill, representing a 4.90 per cent decrease from the N7.03 billion allocated in 2025.

The proposed budget comprises N6.04 billion for personnel costs, N233.6 million for overhead, and N410.8 million earmarked for capital projects.

While some stakeholders commended government efforts to revive the company, particularly in line with President Bola Tinubu’s economic diversification agenda, others raised concerns about the possibility of mismanagement.
Philip Jakpor, Executive Director of Renevyln Development Initiative (RDI), questioned the continued funding of the steel plant despite its prolonged inactivity.

Jakpor alleged that previous administrations repeatedly used ASCL as a channel to access public funds without improving its operational status.
“It seems it has become a cash cow for some individuals in every administration; They pump billions of naira into its rehabilitation and yet the mill does not work a single day.
“So, we are not surprised that this administration has again budgeted N6.69 billion for it in the 2026 Appropriation,” he said.
Similarly, Abdullahi Jabi, Chairman of the North Central Zone of the Campaign for Democracy, Human Rights Advocacy, and Civil Society of Nigeria, stressed the need for fiscal discipline to ensure effective budget implementation.

Executive Director of Renevyln Development Initiative (RDI), Philip Jakpor


According to him, frequent budgetary ‘somersaults’ have continued to undermine Nigeria’s industrialisation drive, particularly within the steel sector.
He said critical sectors such as steel production must be prioritised, with the engagement of professionals and specialised manpower to stimulate economic growth amid prevailing challenges.
“Critical areas should have impact on the people beyond the signing of MoUs without what to show for it.
“We need a paradigm shift as promised in the electioneering campaign,” he said.
Emmanuel Shuiabu, a former resident of ASCL, recalled living in Ajaokuta between 1982 and 2002, noting that the company was once Nigeria’s largest employer, providing over 10,000 direct jobs.
He said the company’s Thermal Power Plant and Turbo Blower Station previously operated at full capacity, adding that the community enjoyed uninterrupted power supply between 1987 and 1989.
Shuiabu expressed concern over the current state of the plant, stating that beyond political will, decisive and practical political action—particularly engagement with the original builders of the plant—was necessary to achieve meaningful progress.
“The challenge with government is the lip service they pay to some things that are meant to drive industrialisation in Africa, because ASCL is the largest steel plant in Africa,” he said.
He further recommended that experienced professionals who previously worked at ASCL be engaged in the revival process, even if it requires recalling retired personnel.
Shuiabu, also a finance expert, noted that despite concerns over rising budgetary allocations to the plant, not all approved funds were usually released during implementation.
The Minister of Steel Development, Prince Shuaibu Audu, stated in his New Year message that despite the non-release of 2025 budget funds, the ministry sustained reform efforts through prudent utilisation of the 2024 Appropriation.
A Lokoja-based public analyst, who requested anonymity, said activities at the plant were largely limited to maintenance, adding that attempts to verify claims of new developments had been unsuccessful.
“They are just maintaining the place so it does not collapse. It’s like keeping the brain alive in case the human body wakes. The same situation also exists at the Jos Steel Rolling Mill,” he said.
Victoria Ola, a former staff member who once lived in the company’s quarters, said communities around the steel complex had declined significantly, contrasting sharply with the once vibrant socio-economic activities in the area.
Ola, however, urged Nigerians to remain patient, noting that government efforts to revive the plant could help reduce the country’s overdependence on oil.
A government official, who also requested anonymity, said most of the allocated funds were directed toward personnel costs required to maintain the facility, while capital projects accounted for only 6.1 per cent of the total budget, an amount considered insufficient to deliver major short-term transformation.
Earlier, Prof. Linus Asuquo, Director-General of the National Metallurgical Development Centre, Jos, disclosed at the maiden National Steel Summit in 2025 that ASCL costs Nigeria over N1 billion annually in pensions, salaries, taxes, and administrative expenses.

Nigeria’s Minister of Steel Development, Prince Shuaibu Audu (Nigerian Mining)
Nigeria’s Minister of Steel Development, Prince Shuaibu Audu

The Minister of Steel Development, Prince Shuaibu Audu, also disclosed in his New Year message that Nigeria had made progress in discussions with prospective Chinese investors to support the revival of the Ajaokuta Steel Plant.
He added that the ministry facilitated a 500 million dollar investment by the Nigerian National Petroleum Company Limited (NNPCL) and its partners for the establishment of five mini-Liquefied Natural Gas plants within the Ajaokuta Steel complex.
Audu further stated that the ministry signed a Memorandum of Understanding (MoU) with the Federal Ministry of Defence for the local production of military hardware and the establishment of a Military Industrial Complex within the Ajaokuta Steel Company.
He said the project would be executed in collaboration with the Defence Industries Corporation of Nigeria.